(8- 17 June) are from Vasile who sends me almost daily WhatApp updates. I return to Formentera on June 19th, so will resume in next post.
June 1st: building the roof for the cisterna
Concrete
Dry, but still partly shuttered
The finished structure. Now needs plumbing (three inlet pipe holes for rain water),
waterproofing and painting inside. Pump house will be built above access hatch,
with feeds to house and pool plumbing. Then the surrounding excavated hole will be backfilled to ground level.
The house is nearly full height on the left
Max came to visit. He loved the building site! Great climbing frames.
Pool east wall being shuttered. All pipes and lights fitted.
Detail of one light fixture (there are three) and one pipe (this one is for a jet).
There are three at the bottom of the pool, two for heated water inlets,
one for heated water return. And four at the top of the pool, three jets and one vacuum.
Pouring concrete to pool east side
Dry and set
Unshuttered East wall
Removing all shuttering
Last one
The finished pool structure
Now start building the overflow basin using concrete blocks
(it doesn't need to be a strong as the pool itself)...
(it doesn't need to be a strong as the pool itself)...
...and the machine room, also concrete blocks
Machine room roofed.
...and the house grows as well,
...with the roof for
the hall and study going up.
the hall and study going up.
Lintels are all home built of reinforced concrete, extending 40 centimetres each side in case we ever want to widen the windows (or doors)
Pano of the full house
Working late ...




No comments:
Post a Comment