Kitchen sliding 'window and shutters' about to be installed...
... in position. Left part will be bricked in.
Same thing with sliding doors. This is the living room door installed...
... and with the sides bricked in. All windows and doors are iroko hardwood (https://en.wikipedia.org/wiki/Iroko).
The remaining door and window frames have also been delivered
We spent eight hours over two days with the plumber and electrician marking up all the ducting, power points, light points, air-conditioning ducts, and then started on cutting them in.
There is no logical significance to red and blue paint. We ran out of blue...
Three sockets on either side of bed,
two switches above one for wall light, one for reading light,
reading wall lamp above that.
Ceiling recessed downlighter in guest bathroom
Duct markings and cut-ins.
Back to the roof ...
Final layer of cement. Next come tiles and finishing parapets with 2 layers of cement.
Arlita on master bedroom roof.
Cutting in chimney for wood burner. We're going for a Bronpi 'Dover'.
Bronpi 'Dover'.
Building the chimney for the wood burner, left, and right the kitchen extractor exhaust...
... and then, when waterproofing is done, fill with water. No leaks!
Detail of rain drain from one roof surface to the next. This one is yet to be waterproofed.
The house at the end of this week.







Is the underfloor heat water (or air or electric)?
ReplyDeleteWater, heated by solar on roof via heat pump.