28 August to 2 September
Finish the parapets and some levelling of roofs, and do as much internal brickwork as possible without the carpenter.
Shuttering for the 'petos' (parapets) on master bedroom
Reinforced concrete poured for master and guest bedroom petos.
Building up the skylight to master dressing room, and parapets to master bedroom; and on the right, the un-shuttered parapets to hallway and study.
Continue with internal brickwork in master bedroom, with built-in shelving going in.
4 to 16 September
Install the built-in flush tanks for toilets, build the lintels for sliding doors in living room, master bedroom and kitchen window. Continue insulation and arlita on roofs where no ducting is required. Waterproof guest bedroom roofs and fill with water to check for leaks. Sliding doors are delivered (living room, master bedroom) along with sliding window for kitchen.
Insulation and prep for arlita on guest wing roof.
The pipe in far wall is the toilet air exhaust.
Toilet flush tank, one of three. The frame supports the hanging toilet pan.
Water inlet pipe is bottom left, will run underfloor.
Lintel for master bedroom sliding doors and shutters
Lintel for kitchen sliding window and shutters
Doors being delivered
Tela asfaltada membrane
Water check
Sliding door nearly in place