Hallway plastering done
Guest bedrooms plastering done
Kitchen plaster drying
The boys are working on the living room second coat of plaster
...and the terrace ceiling has been rendered as well
First we fill the terraces with hardcore, ...
...then with sand and gravel. This will be compacted, the rain pipes will then be placed in,
and the lot will be covered with reinforced concrete. Then tiles.
and the lot will be covered with reinforced concrete. Then tiles.
The window frames are installed in the study/trastero,
and the stone facing for the study is growing well,
and the stone facing for the study is growing well,
up about a metre. This is the East side.
On the north side it's also moving well. The pipe is the air intake for the underfloor ventilation.
Detail of the lintels I made for the guest bathroom windows. I decided to make another one for the wide study window, with thanks to Bill for the beautiful piece of sabina.
Starting to strip the bark off this chunky piece of juniper.
Part done. The hardest task is getting all the knots clean.
One day later. By the time I leave on Monday 18th Dec, it's been sanded and treated and is in Mo's hands to install when the stonework is up to window lintel level.
We also finished a lot of small jobs. Here we ran a pipe for the A/C drip
and finished the master bedroom floor.
Site meeting with architect and plumber to finalise details of bathrooms.
I leave on Monday 18th Dec. Beautiful day. Work will slow down from the end of next week until after the Dia de los Reyes on 6 January, however Mo and Manzu will carry on building up the stone walls. Once the internal walls are all plastered and the bathrooms are built we'll put down the underfloor heating and finish the floor. See you 2018!