Wednesday, 11 April 2018

Week 51 (but really week 52) - 9 to 14 April 2018 - Carpentry and more...

Where did week 52 go? We started work on 12 April 2017, so next Thursday will be the first anniversary of the build project. I must have miscounted some where along the way and missed a week.

The builders have some urgent work on other sites, and as we're waiting for tiles to be delivered anyway, and also because the weather is foul - strong winds, rain, chilly - we decided to slow things down this week. Moussa does some work on windows, some plumbing materials are delivered, but that's about it.



The first window is fitted in the trastero. 
All of the smaller windows will have a 'porticon', the internal solid door. Glazing will come later.



The same from outside.



Michael and Sally at Cala Saona on Sunday.



Front inner doors are fitted. Outer solid doors will be double pane and will come later.



Window in guest hallway. Portion is shown closed.
Glass coming later.



Interesting pano taken by Michael. Cold and windy day!



Remaining windows (with portion fitted) are delivered.



Copper pipes and insulation for heat pump.



Windy, grey days...

Next week we'll fit the remaining windows and shutters, and we plan to start up on the external rendering and remaining tiling.





3 comments:

  1. Looking good and definitely better place to be given weather in UK

    ReplyDelete
  2. Michael Fasosin19 April 2018 at 13:15

    Loving the windows they're gorgeous. Can't wait to see them. Did the glass go in the doors. I can't tell? xx Michael

    ReplyDelete
    Replies
    1. Very slow week, little got done, just a few more windows. Remaining windows the week after, then sliding window and doors, then glazing.