Monday, 2 April 2018

Week 50 - 2 to 7 April 2018 - Finish tiling the pool and start on carpentry.


Easter Monday: we finish tiling the pool! It won't see water for a while: we will grout on Tuesday, and then tile the overflow basin, either with mosaic tiles or with more of the same, install pumps, filters and power in the machine room later.



The pool is tiled! Tuesday we start grouting.



A grouted pool!!!



Tuesday evening.



Making sills for the persianas on guest bedrooms.



We have to put a gate on the stairway to heaven. Regulations.



Banister is set in.



Manholes built.



Chimney and extractor outlet. Covers being made as I write.




Internal doors were delivered Thursday morning and are being fitted today (Thursday).
Aren't they beautiful? Solid Iroko!


First two are in.



Detail of doors



Carpenter's tools.



Inner doors going onto guest bedrooms. Glazing later...



Fitted the cover to one of the chimney breasts. I will cut down the pegs to about 10-12 cms.


Work slows down at the end of the week. The carpenter will start on windows next week, but bad weather is forecast so we'll see how far we get.