Wednesday, 16 May 2018

Week 56 - 7 to 12 May 2018 - We're back!

Not a lot happened in the three weeks we were away. Poor weather prevented the gang from starting on the external rendering, and other issues kept the workers away. Now we're back things have picked up. Antonio assures us that the house will be ready by the first week in July. We'll see...




We decided to tile the pool overflow basin with the same tiles as the pool and terrace. This is work in progress. More tiles are on order.



Glass has arrived. Most doors and windows were glazed on Tuesday. 



Master bedroom sliding glazed and external doors.



External front doors delivered!



... and now fitted.



West elevation doors.