Guest bathroom plaster. Microcemento to come.
Living room plaster.
Living room from the other side. Rubio is touching up.
External rendering all done, and garage underfloor laid.
Pool plumbing is done as well, including salt electrolysis system.
Garage subfloor and plumbing for underfloor heating system. Air-source heat pump will go in corner, and solar panel system is ready for installation on the roof. Hot water system will go on left wall.
South facing wall showing rendering and air-source heat pump fan installed.
All windows and doors are now glazed.
Master bathroom plastering.
Guest bedroom plastering.
Saturday morning, the flatpack (Ikea) kitchen arrives. Only 4 items are missing... It'll stay in the garage until the painting and electrics are finished. The boys were in all day cleaning the house with compressed air hoses, ready for painting next week. Tomorrow is day of rest.