Wednesday, 19 July 2017

Week 13 ----- (17 to 22 July 2017) ----- Main structure almost finished.

The pine beams for the main roof arrive this week. We build up the supporting columns for the terrace roof and the main beam in the living roof, prepare the sockets for the cross beams, start on the stairway to heaven - which requires a bit of jiggery-pokery to get the angles right - and generally work on getting all the elevations right to receive the beams.



Hi-tech planning of beam structure



Terrace support column, with rainwater drain



Cutting in the cross-beam support sockets



Vasile and angle grinder



Stairs to roof... we're still working on the angle and elevations...



Shuttering for the lintel above sliding door to terrace from living room


Wednesday morning: Beams are delivered. Spend the afternoon unloading and checking stock. It all appears to be there. Now we need to treat the wood, then start mounting. Very heavy stuff, so it will be chain saws, crane and lots of sweat and tears...



The 'plataforma' has arrived!



Lotsa wood



Patio posts (30 cm diameter) are not what we ordered, and will be sent back; living room main beam (30x25 cm), terrace beams (14x14)



Living room beams (20x15) and terrace front beams



Hoisting 3 tons of wood onto the roof

This Wednesday morning, while waiting for the crane to unload the trailer, we scribed in the stairs to the roof, built the shuttering for same, and finished the shuttering for the rest of the living room roof-line.



Shuttering for top of stairs. Decided to put a small (80x80 cm) tiled floor at top of staircase instead of taking steps to top.



Stairs shuttering started



Moved the stairs profile to clear the garage door. Old line in white, new line in red. Raised tread height to 20.3 cm from 19, tread depth is 28cm. This gives more clearance.



Shuttering for roof line concrete reinforcement all lined up to receive beams. The living room roof will be supported by and built above the beams which provide structural support.



Heaven



Last two days of this week spent distressing and treating the main beams for the living room.
These are the 20 x 15 cm cross beams, 5 metres long.




This is the main beam. A huge piece of wood, 25 x 30 cm and 4 meters long.



We're getting there, but a lot more to do.



Untreated beams ....




1 comment: