Thursday, 6 July 2017

Weeks 10 and 11 ----- (26 June to 8 July 2017) ----- Start reinforced concrete roofs

I left Formentera on Friday 23 June, and lo and behold, very little happened the week after. In fact nothing. Deliveries arrived on Monday 3rd July, at the same time as Sally and I arrived back on the island.
On Tuesday morning Vasile and the boys arrive early to finish the shuttering for the roofs. On Wednesday they got the concrete mixer going and poured the roofs for the guest wing, hallway and master bathroom.

Some photos...


Deliveries



Structure of overhang for living room wall, with study and truster roof behind ready for steel and concrete.



Detail of the steelwork



 Master bathroom roof structure



Current state



Guest wing roof stage 1, parapet steel in



Guest wing roof stage 2, blocks and beam steel in



 Guest wing roof stage 3, concrete in



Cisterna



Cisterna roof from inside



 Shutters for porch column and footings



 Hall roof done



Big fire in Es Cap this afternoon (5 July). Two helicopters and two planes dropping water.



Later this week Karim applied two coats of waterproofing to the inside of the cistern, and the boys have built the 'encofrado' for the master bedroom, poured the porch footings and worked on the other roofs.


Samples of concrete for analysis



Encofrado for estudio



Stairway to heaven



Front entrance



The house as it stands now