Tuesday, 15 August 2017

Week 17 - (14 to 19 August 2017) - Internal insulation and walls

The boys have run out of 'arlita' (more on order) so have moved inside. Finish the brickwork in the master bathroom, do the brickwork in the 'guest wing' and living room. Some of it is pretty straightforward, but some of it is quite tricky and involves a lot of cutting for angles around doorways.

Sunday 13 August

Sally and I played around with kitchen designs, using insulation plates that happen to measure 60 cms by 120, just perfect.



Yes, it is a kitchen!


Monday 14 August



Internal brickwork in bathroom.



Positioning a 'nicho' in the shower, a recess for shampoo bottles, all carefully measured!



Internal brickwork in guest bedroom 1.



Preparing the guest hallway for lining bricks and air gap insulation.


Tuesday 15 August 2017



Brick lining On hallway. 1 cm air gap for insulation.



Hallway almost done



 Start on the living room back patio door frames



Detail of the door jambs



Start on guest bathroom



Guest bedroom 1 done except for lintel above door. Tomorrow.



Wednesday 16 August


Lintel above bedroom 1 patio door. Cast concrete, framing still on.



Lintel for master internal bathroom door. Made of ladrillos, iron and concrete.



Start on one of the living room built-in shelf units. Cast concrete shelves.



Detail of shelves. Bottom one done, second one drying, framing still in-situ.



Guest bathroom wall done. This is from the bedroom side,
 which will house a large wardrobe.



Guest bathroom cupboard, and shower to its right.



Shopping list for this week.
4 pallets of arlita (ceramic beads for roof forming),
300 square metres of insulation,
20 bags of quick setting cement,
300 square meters of roof insulation,
70 square meters of 9 x 20 x 30 ladrillos (bricks)
.....



House as it is at the end of the day. The roof line will be taken up a bit,
and rounded off, all in cast concrete.


Thursday 17 August


Building another lintel, above the living room door to the NE patio



Detail



Framed and poured



How the living room is shaping up



Garage support struts mostly removed.
We plan to remove the roof shuttering next week.

Friday and Saturday 18-19 August


Shuttering built for 'petos' (parapet) top.







Concrete poured and formed on 'petos'.



First of two deliveries! Arlita, insulation, ladrillos. Next week's work!