As an aside, I have created a new blog with just a summary of the main stages. It is at https://casa-sally-short.blogspot.co.uk
Most supporting struts have been removed in the living area
and we can start seeing what the living room will look like.
Master area, most struts removed. Skylight above (to master dressing room)
and living area beyond. Pic taken from master bathroom.
Main pine beam dividing living and dining areas. Entrance hall beyond.
Porch, aka terrace. The opening on the left will be sliding doors to living room,
the opening on right is window to kitchen (also sliding into the wall).
Porch/terrace with shuttering removed.
On Friday, the boys start on the interior. First a light skim of cement on the concrete block walls to seal any small gaps, then 'corcho', which means cork but is in fact 3 cm thick polystyrene insulation. Then will come a layer of fairly thin 'ladrillos', the terra cotta bricks they use down here, with an air gap between them and the insulation layer. Then render and paint, eventually. Plumbing and electric ducting will be cut into the ladrillos as needed.
Master bathroom insulation going on.
The rectangular 'hole' is where we'll have a recessed niche for shelving.
To the right of the 'niche-to-be' is an evacuation pipe for the underfloor airflow
through the 'cavitis'. This will be hidden by the brickwork.